ABBYY FlexiCapture excludes tasks with the extra-high priority from this rule and processes them before overdue batches.
Specify a processing deadline
You can specify time constraints for batch processing on the Project Setup Station. The specified period begins when documents are scanned on a Scanning Station, if one is used, or when the batch is created on the server.1
Open the properties dialog box
Open the properties dialog box of the project or a batch type, and select the Workflow tab.
2
Enable the time limit
Enable the Enable processing time limit for batches option, and then click Set Time Limit….
3
Set the time limit
In the dialog box that opens, specify the time allowed to process the batch using the Batch processing time limit N minutes/hours/days option.
- Automatically, based on the number of outstanding processing stages and the number of pages in the batch
- Manually, using the Warn in N minutes/hours/days option
<overdue minutes> * <pages left in the batch>). It calculates the overdue minutes using a rough estimate of how long it takes to process a batch.
Use scripts to specify SLA settings
You can use scripts to set up time constraints for batch processing and the period during which ABBYY FlexiCapture displays deadline warnings. Scripts can specify more complicated settings, such as time constraints that take employees’ working hours into account.You can use scripts to specify SLA settings only in custom batches of any type other than Default.
1
Open the Properties dialog box
Open the Properties dialog box of a project or a batch type, and select the Workflow tab.
2
Enable the time limit
Enable the Enable processing time limit for batches option, and click Set Time Limit….
3
Enable the script option
Enable the Set processing time limit with script option, and click Edit.